Thursday, August 7, 2008

Slab Poured! - Week 5 Thursday - (Day 32)

Dropped by on my lunch break today and the slab was poured yesterday. We are very happy with the progress so far. Hopefully the weather holds good for a while so that this sort of progress continues!

This is the slab taken from the front corner of the house (where the garage entrance is) looking over to the rear of the block

This from the Eastern corner from the same location of previous posts. In the foreground will be the study with the main entrance in the middle and then the garage front

This is the view from the south looking north. In the foreground is the Alfresco. The main bedroom will have a door to the Alfresco to the left as you look at it here. The other door to the Alfresco is from the living / TV area to the front.

This is a view from the block behind us looking over the fence. Here you can see the whole slab.

Apparently the frame will be delivered by tomorrow, so they should make a start on the frame next week after the Show Holiday on monday.